COVID-19 Crisis
Image source - https://go.ey.com/2VtRhcl

This article is written by Vishesh Gupta from Institute of Law, Nirma University, Ahmedabad. This article discusses the importance of renegotiations of contracts in the times of COVID-19.

Introduction

The whole world is currently facing one of the biggest crises in the modern era. COVID-19 has spread all around the globe. The World Health Organisation has declared it to be a pandemic and many countries including India, United States of America, Singapore have imposed extreme measures of “Lockdown”.

The novel coronavirus has severely affected the global economy and commercial market. International trade including export and import, the international movement of people from one country to another and businesses have been effectively stopped for an indefinite time.

In these challenging times, one has to think about the impact of the lockdown on his previously entered contractual obligations. Therefore, this article discusses whether a contract could be renegotiated during this COVID-19 crisis. This article also puts light on the importance of renegotiations of contracts during COVID-19.

Why is there a need for renegotiation of contracts? 

The highest law in any commercial contract is the principle of Pacta Sunt Servanda which means that agreements must be kept and must be performed in good faith. However, because of the COVID-19, the world is in a state of lockdown and supply chains have been disrupted and the demand and supply curve has also been reduced. Any import or export is not allowed.

Businesses have been exposed to heightened risks of legal implications which impacts the small companies and manufactures more severely than the large Multinational Corporations. Even these MNCs are not entirely unaffected.

Global trade and the world economy are in shambles and it has a direct consequence on every individual. In these circumstances, it is difficult to conduct business and fulfil any previously entered contractual obligations.

Therefore, parties to the contract seek to absolve, delay, or alter the terms of their contractual obligations so as to minimise any unjust costs and legal implication. 

Can a contract be renegotiated in the light of COVID-19? 

A contract could be renegotiated when the subject matter of the contract becomes impossible to perform. This is a common law principle also known as the frustration of contraction. Further, parties can invoke the clause of Force Majeure (if it is drafted in a contract).

Generally, a well-drafted contract always contains the Force Majeure Clause so as to save the parties from any unforeseeable loss or liability which involves no fault from the parties. 

Force Majeure Clause

Force Majeure is one of the essential clauses in a contract which protects a party from liability for the failure of performance of the contractual obligations because of unforeseeable events which are beyond the control of the parties. 

For instance, In the case of Peter Dixon and Sons, Ltd. v. Henderson Craig and Co. Ltd. (1919) 2 K.B. 778, British ships were no longer available because of the war for carriage of wood pulp from Canada to Grimsby in England. It was held to be a hindrance to the performance of a contract for delivery of pulp and came within the meaning of the force majeure clause in the contract under consideration in that case. It was held that the boilers were not liable for non performance of shipping pulp.

It has not been expressly mentioned in the Indian Contract Act but it derives its authority from the doctrine of frustration which is mentioned in Section 32 and Section 56 of the Indian Contract Act. 

In the case of Energy Watchdog v CERC, (2017) 14 SCC 80, it was clearly stated that force majeure is governed by the Indian Contract Act. If the force majeure clause is mentioned in a contract, it is governed by Section 32 of the Indian Contract Act. However even in the cases where force majeure event is outside the scope of the contract, it will be governed by Sec 56 of the Indian Contract Act. The latter is known as the doctrine of frustration and will be discussed in the next section of the article.

Force Majeure includes the Act of God, war or war-like situations, labour unrest or strikes.

It is pertinent to note that force majeure and Act of God cannot be used interchangeably. Force Majeure is a broader concept than the Act of God as force majeure includes an act of god and any event which involves human agency unlike events in the Act of God. The rationale behind the Force majeure provision is to protect a party from the consequences of a breach of contract on which the party has no control.

Whether COVID-19 is covered under Force Majeure?

There is no universal answer to this, but Indian and Chinese governments have answered this in affirmative. The legislative body and the judiciary of China have effectively categorized COVID-19 outbreak Corona under Force Majeure. The China Council for the Promotion of International Trade issued over 1,600 ‘force majeure certificates’ to Chinese companies in February. 

In India, the Department of Expenditure, Procurement Policy Division, Ministry of Finance issued an Office Memorandum on Feb. 20, 2020, in relation to the Government’s ‘Manual for Procurement of Goods, 2017’. The Memorandum has effectively stated that the COVID-19 outbreak could be covered by a force majeure clause. 

Also, in some cases, the question of whether pandemics, in general, could be covered in force majeure can be answered by expressly including pandemic in Force Majeure clause of the contract. In cases of contract law, a well-drafted contract is essential. Every liability and responsibility is determined based on what is written in the contract.

It may be general in nature where the Force Majeure clause is included in the contract but has not been defined in specific terms. On the other hand, the exact scope of Force Majeure has been expressly written. Proving pandemic as a force majeure event is more difficult in the case where the clause of Force majeure is not defined in specific terms. 

Doctrine of Frustration 

Even if a contract does not contain the Force Majeure clause, parties to the contract can rely on the common law doctrine of frustration as Force majeure derives its authority from this doctrine. 

The doctrine of frustration is embodied in Section 56 of the Indian Contract Act which states that if an act becomes impossible to perform the contract shall be deemed void. 

The court, in the case of Satyabrata Ghose v. Mugneeram Bangur and Co., stated that if the event was outside the anticipation of the contract, Section 56 of the Indian Contract Act would apply and render the contract void even if no implied or express provision regarding Force Majeure was present. In this case, Satyabrata(plaintiff) sued the defendant for wrongfully repudiating the contract of developing the land. Defendant took the defence of frustration as the land which needed to be developed were temporarily requisitioned by the Government under the defence rules for an unspecified period of time. The court declared that the contract had not become impossible to perform as the circumstances of war were known to the parties and the reasonable time in which the contract was to be completed was not mentioned.

https://lawsikho.com/course/diploma-advanced-contract-drafting-negotiation-dispute-resolution
          Click Above

What things are to be taken care of before enforcing force majeure?

  1. Duty to Mitigate- The provision of Force Majeure has been misused in a plethora of cases as a means to escape the contractual obligations. The party invoking the exception of Force majeure has the burden of proof to show that there were no reasonable measures to mitigate or avoid the consequences of the force majeure event. 
  2. Notification requirement- Force Majeure clause contains a time-bound notification requirement. Such provisions are enforceable, and so complying fully with all notice requirements will be important for parties seeking to invoke the exception of force majeure.
  3. In cases of the renewable energy sector, companies claiming for time extension shall submit an application to Solar Energy Corporation of India Ltd (SECI) or other implementing agencies. Companies also have to provide all evidence in support of their claim and on reviewing all the evidence, agencies may grant Extension of Time.
  4. Defence of economic hardship is not adequate to invoke frustration of the contract. The doctrine of frustration does not relieve a party from performing their contractual obligation simply because the force majeure event has made the performance more difficult or expensive.

Benefits of Renegotiations

The circumstances at the time of the formation of the contract are always fluctuating and sometimes the unexpected events change these circumstances in such a way that the execution of the contract in the new conditions, without the adjustment/renegotiation of contract, makes the performance extremely difficult and unbearable. 

The rapid spread of COVID- 19 around the world was not reasonably foreseeable by anyone. So, any contractual obligation or performance of a contract that seemed possible in December 2019 and January 2020, is now almost impossible to perform because of the complete lockdown.

Breach of contract is justiciable in a court of law and may cause unjust losses to the parties. Renegotiation is an effective way of modifying various aspects of a contract which is more suitable to the prevailing situation of the market and the world in general. 

Looking at the current developments of COVID-19 in India and the rest of the world, there remains huge uncertainty about when the normalcy will prevail again. So any contract, whose performance is due now or in a foreseeable future should be considered for renegotiation of the terms of the contracts. 

Remedies for Force Majeure Event 

The wordings of the contract would determine the future course of Action when the Force Majeure event takes place. 

  1. Termination of Contract: Parties may terminate the contract in toto or suspend only a few clauses of an agreement. 
  2. Freezing of contract: Some parties may decide to put on hold the contractual obligations until the force majeure event is over.
  3. If the force majeure event is prolonged, a clause of termination will be enforced in a certain period of time as prescribed in the contract. 

However, this is not applicable in all cases. For instance, for a contract in which perishable goods are the subject matter, freezing or prolonging the contracts is not reasonable. 

Scope of Re-negotiation clause in contracts 

The concept of renegotiation tries to uphold the principle of pacta sunt servanda. Scope of Renegotiation can be found in the terms of the contract itself. There may be a clause of renegotiation which specifies in which circumstances can the contract be renegotiated. Renegotiation clauses include cancelling/absolving the contract, delaying the obligations till future notice when the contract could be enforced. 

Renegotiation may also exist in different clauses like material adverse change clauses, to limit or exclude liability for non-performance, price adjustment clauses, limitation or exclusion clauses etc.

Material adverse change clauses state that if the status of the subject matter or the status of the parties has adversely changed since the time when the contract was entered, the contract will be deemed to be void. This clause is commonly found in acquisition, merger and lending agreements. 

These clauses provide flexibility to a contract and the main reason for the inclusion of these provisions is to ensure that parties do not face losses and that the contract could be performed, not as originally agreed, but in such a manner as to reduce risk of losses and legal implications.

Renegotiation for different subject matters

In the current scenario, renegotiation shall differ for contracts involving different subject matter. It is important for a party to a contract to decide whether they want to absolve the contract altogether or they want to prepone or postpone the commitment.

  1. Essential commodities: As we all are in the state of lockdown, the supply of essential commodities like groceries and medicines are very important and therefore, the contracts of supply of these commodities shall not be absolved. The terms of the contract regarding the time period, jurisdiction covered, mode of performance and consideration can be altered. This is more applicable to those vendors who don’t have a huge supply chain. 
  2. Renewable Energy: The government is offering leniency in the renewable energy sector as the renewable energy sector can cite COVID-19 as the force majeure to delay the projects. This is because this sector may face project delays because of COVID-19, which could prove fatal to the country’s flagship 175GW target for 2022.

Absolving the contract in toto should be used in those cases only where the performance cannot be possible for a foreseeable future and in the cases where the time of performance of the contract is of the essence and non-performance at the stipulated time will lead to non-recoverable losses.

Effects of force majeure certificates issued by Chinese government 

The certificates will no doubt be beneficial to chinese companies in the domestic market, but these certificates might not hold up at the global stage as other countries have strict terms for claiming Force Majeure. 

Further, many companies in China have contracts that call either for disputes to be adjudicated in jurisdictions other than the Chinese courts or arbitration forums or to apply laws other than China’s. Outside China, the legal value of those certificates is unknown. 

Conclusion

The crisis that humanity is currently facing has no end date confirmed. No vaccine has been created and the virus is spreading like wildfire. Determining the date when the world will return to normalcy seems implausible. This puts uncertainty in most of the contracts which are currently impossible to perform and this ultimately affects the parties as non-performance leads to losses for the parties involved in a contract.

However, a well-drafted contract can save a party from losses. A well-drafted contract is a contract that anticipates any loss that parties might incur and also don’t put any additional burden on the parties.

Contracts should have the force majeure and renegotiation clause as it provides more flexibility to the contract. In these uncertain times, a contract should be renegotiated in such a way that it becomes possible to perform in these uncertain times.

The role of advocates is of great importance for renegotiating contracts. The intricacies of a contract could be understood by an advocate and he can guide the parties towards amicable discussions for renegotiations. It is advisable to keep an open mind during renegotiations so that parties could make the best of the worst situations.


LawSikho has created a telegram group for exchanging legal knowledge, referrals and various opportunities. You can click on this link and join:

https://t.me/joinchat/J_0YrBa4IBSHdpuTfQO_sA

Follow us on Instagram and subscribe to our YouTube channel for more amazing legal content.

Did you find this blog post helpful? Subscribe so that you never miss another post! Just complete this form…

1 COMMENT

LEAVE A REPLY